The Water Infrastructure Finance and Innovation Act (“WIFIA”) loan program offered by the United States Environmental Protection Agency, could be a valuable component of a water project financing mix. The key advantages of the WIFIA loan program include:
The WIFIA program was introduced in 2017 with the goal of accelerating the development of water infrastructure projects in the United States. The following project types can be funded through the program:
WIFIA can finance only new projects and cannot be used for existing debt refinancing.
Through June 2022, the program has funded 88 loans totaling $15.3 billion in proceeds.47 (53%) of these loans exceeded $100 million in proceeds. 45% of the WIFIA funding was used for wastewater projects. The most up-to-date information about WIFIA loan issuance can be found here.
WIFIA is open to:
The minimum project sizes are:
The program staff has been making an active effort to accommodate smaller communities.
Multiple projects can be funded under one WIFIA loan, as long as the repayment source is the same. This is a feature that can help reduce loan fees.
A major advantage of WIFIA is its ability to fund project construction. Unlike the USDA, which often requires borrowers to obtain separate construction financing, WIFIA can be set up to fund as a series of construction draws. This allows for lower overall interest cost, since interest is accrued only on the outstanding loan balance.
WIFIA can fund capitalized interest during the construction and deferred repayment periods.
Construction draws can be submitted monthly.
Another advantage of WIFIA is the ability to defer the commencement of the loan payments and to shift a large portion of the principal repayment towards the later years of the loan.
The loan repayment can be deferred for up to 5 years after the substantial completion of the project, which means that the term of the WIFIA loan can be for up to 42 years (two years for project construction, five years of deferred repayment, and then 35 years of amortization). The interest rate would remain fixed throughout the term of the loan.
The repayment schedule can be structured to back-load the principal repayment towards the later years, if necessary. While such back-loading results in the higher interest cost over the term of the loan, it may be beneficial when viewed in the overall project or system debt repayment context. The delayed principal repayment of the WIFIA loan can be valuable under the following scenarios:
WIFIA can fund capitalized interest during the construction and deferred repayment periods.
The WIFIA funding is limited to 49% of eligible project costs (plus capitalized interest).
The program also falls under the 80% federal funding limitation rule, which can come into play if the USDA financing and federal grants are also used to fund the project.
Since the State Revolving Fund (“SRF”) programs are only partially dependent on federal funds, they generally do not count towards the 80% federal funding limitation.
While WIFIA will not fund an entire project, it could be a very valuable and powerful addition to the funding mix, supplementing other State Revolving Fund, USDA, grant, and bond funding and allowing for proactive debt service structuring.
The interest rate on the WIFIA loans is fixed at the time of approval at the US Treasury (SLGS) rates for the weighted average life of the loan plus 0.01%. This method usually results in a lower interest rate than if the interest rate were to be based on the final loan maturity date.
The interest rate is not impacted by the borrower’s credit rating, which makes the program especially attractive for borrowers that are rated lower than AAA. However, the interest rate should be compared against the tax-exempt interest rates available in the bond and private placement markets.
If the interest rates go down, the borrower can request a rate reduction, as long as no loan draws have been made. The rates adjustment process can take several weeks, requires additional paperwork, and comes with additional fees.
The loan term and repayment commencement are tied to the substantial completion of the project:
If the repayment is deferred, the interest on the loan still accrues and continues to be added to the principal amount of the loan.
There are no prepayment premiums or limitations on WIFIA. The loan can be paid off or refinanced at any time.
To apply for the WIFIA loan, you first must submit the letter of interest after the Notice of Funding Availability is published. If your project is selected, then you will receive an invitation to apply and will have up to 1 year to finalize your application. Once the application is complete, the EPA will take 4-7 months to approve the financing.
WIFIA requires borrowers who do not have a credit rating to go through the rating process with at least one of the four major rating agencies (Moody’s, S&P, Fitch, or KBRA). This is a one-time rating requirement. The borrowers are not obligated to maintain the rating during the term of the loan.
The WIFIA program requires the same environmental review process as the SRF. Incases where the WIFIA and SRF funding is combined, the environmental review process can be coordinated between the two agencies.
WIFIA generates its own loan documents, which can be integrated with other financing documents and the master indenture.
The financial loan covenants are the typical 1.20x rate covenant and additional debt limitation.
The major drawback of the WIFIA program is that it comes with somewhat high fees, which can be an issue with smaller projects.
As of June 2022, the following fees are in place:
The Application Fee is used to offset a portion of the third-party costs incurred by WIFIA (primarily legal, but also other consultants, as applicable).
While no fees are required to submit the Letter of Interest (“LOI”), it is important to keep in mind that once the LOI is approved, the Application and Credit Processing Fees are due regardless of the final loan approval or the borrower’s decision to decline an approved loan.
Once the loan is in place, the borrower is responsible for the one-time loan Set-Up Fee and annual loan Servicing Fees:
These fees are subject to adjustment by WIFIA.
As you can see, there are plenty of reasons to consider WIFIA as a part of your water project financing strategy if you can live with the program’s limitations.
If you would like to discuss the funding strategy for your water project or need assistance with the WIFIA application process, do not hesitate to contact Ridgeline.
Ridgeline's assessment of CalPERS' FY2024 investment performance and its impact on the CalPERS member agencies.
Read this postFire station and apparatus financing is complex. Here we explore the 8 most common financing mistakes made by fire departments.
Read this postFire mitigation fees help fire departments get funding for new facilities and apparatus. Ridgeline’s best practices guide shows how to plan, implement, and manage fire mitigation fees for maximum impact.
Read this postRidgeline served as a municipal advisor on the issuance of the $10,925,000 Water Revenue Certificates of Participation with $12,000,000 in proceeds for the Tehachapi-Cummings County Water District.
Read this post